ODROID-X & ODROID-Q Shipment Ready

ODROID-X and ODROID-Q production has started this week. We will start the shipment from next week. Please refer to the below for the shipment schedule.

– 1st batch from 30th of July : your order between 1st of July and 11th of July : Shipped out 
– 2nd batch from 6th of August : your order between 12th of July and 15th of July : Shipped out 
– 3rd batch from 13th of August : your order between 16th of July and 31st of July :  Shipped out 
– 4th batch from 27th of August : your order between 1st of August and 6th of August : Shipped out
– 5th batch from 3rd of September : your order between 7th of August and 17th of August : Shipped out
– 6th batch from 10th of September : your order between 18th of August and 31th of August : Shipped out

– After all :  in two weeks after your purchasing!
 
The delivery takes around 3-5 days after you receive the tracking number. But, it depends on your country’s customs process. The tracking number will be sent via paypal linked email or Fedex system. Please check your order’s delivery status after you get the tracking number here. 
Fedex : http://www.fedex.com/
The pictures of production line are below. 
 
1. First stage of  process. The machine is “Solder cream printer”.

 

2. SMT machine: Mouting devices on the PCB.

 

3. Entering into reflow soldering machine.

 

4. SMT soldering is done. Ready to inpection process.

* Note: Each board has 2×2 array of actual PCB to increase the production efficiency.

5. X-ray inspection to check soldering quality.

 

6. Factory Lines

The PCBs will move to another soldering machine for various connectors after inspection process.
And then we will perform all the functionality tests.